
CEMENT |
Cement Production Process
Cement is a fine powder which sets after a few hours
when mixed with water, and
then hardens in a few days into a solid, strong
material. Cement is mainly
used to bind fine sand and coarse aggregates
together in concrete.
Cement is a hydraulic binder, i.e. it hardens when
water is added.
There are 27types of common cement which can be
grouped into 5 general
categories and 3 strength classes: ordinary, high
and very high.
In addition, some special cement exist like sulphate
resisting cement, low heat
cement and calcium aluminates cement.
The quarry is the starting point
Cement
plants are usually located closely either to hot
spots in the market or to
areas with sufficient quantities of raw materials.
The aim is to keep
transportation costs low. Basic constituents for
cement (limestone and clay) are
taken from quarries in these areas.
The raw materials for cement production are quarried
using powerful excavators
or explosive materials.
The raw materials are crushed by special machinery
into pieces usually smaller
than 30 millimetres in size.
A two-step process
Basically,
cement is produced in two steps:
First, clinker is produced from raw materials.
In the second step cement is produced from cement
clinker.
The first step can be a dry, wet, semi-dry or semi-wet
process according to the
state of the raw material.
Raw Meal Production
The raw materials transported to the Plant undergo
crushing with the help of
huge crushers and then are either stored separately,
or they are directly driven
to prehomogenization piles. Next, via a fully
automated system, comprising
weighing devices of high accuracy and
conveyor belts, the crushed raw
materials are driven into the mill (roller
mill or ball bearing mill) for further fine
grinding.
The output, labelled as «raw meal», is stored into
special silos for the
homogenizing process, which is carried out with the
help of blowers installed at
the silos' bottoms. Next, the raw meal is
taken to the storage silos wherefrom it
is driven to the silos for the feeding of the
Rotary Kiln, where the intermediate
output, called «clinker», is produced.
Making clinker
For the production of one ton of clinker around 1.6
tons of raw materials are
utilized (70-85% limestone, 10-20% shale etc.) and
over 0.1 ton of coal.
The raw materials are delivered in bulk, crushed and
homogenised into a mixture
which is fed into a rotary kiln. This is an enormous
rotating pipe of 60 to 120
m long and up to 6 m in diameter. This huge kiln is
heated by a 2000°C flame
inside of it. The kiln is slightly inclined to allow
for the materials to slowly
reach the other end, where it is quickly
cooled to 100-200°C.
With the usage of cyclone system and a limestone
grinder, the raw meal, prior to
it’s feeding into the Rotary Kiln, undergoes
thermal processing at 900 degrees
C. The Rotary Kiln temperature is gradually
raised up to 1450 degrees C and its
final output, which is in granular form, is
the result of the chemical
decomposition of CaCO3 and of the alumina-silicate
compounds and the result
of chemical reactions between CaO and the oxides of
Si, Al and Fe which are
thus produced.
Four basic oxides in the correct proportions make
cement clinker: calcium oxide
(65%), silicon oxide (20%), alumina oxide
(10%) and iron oxide (5%). New
compounds are formed: silicates, aluminates
and ferrites of calcium. Hydraulic
hardening of cement is due to the hydration
of these compounds.
The final product of this phase is called “clinker”.
These solid grains are then
stored in huge silos.
From clinker to cement
The second phase is handled in a cement grinding
mill (made of metallic
cylinders, containing several tons of grinding media,
that are necessary when
the grinding process takes place), which may be
located in a different place to
the clinker plant.
Gypsum (calcium sulphates) and possibly additional
cementitious (such as blast
furnace slag, coal fly ash, natural
pozzolanas, etc.) or inert materials (limestone)
are added to the clinker. All constituents
are ground leading to a fine and
homogenous powder.
Clinker is the basic ingredient of cement, and it
largely determines the quality of
the end product. Cement, as a finished
product is a very fine powder that
requires for its manufacture a mix of clinker,
gypsum and certain natural or
artificial materials (such as pozzolana),
which grant beneficial properties to the
cement. The cement mills resemble the raw
meal mills. The exact mix of
materials is strictly specified and
continuously monitored. The type of cement
and level of compressive strength - which is
the most important characteristic -
depend on the chemical composition of the
clinker, the duration of the grinding
and the presence or absence of various
additives.
The cement is then stored in silos before being
dispatched either in bulk or
bagged using special silo trucks or ships.
Engineering on Cement Plants
A cement plant is a group of complicated and complex
installations. It is composed by a variety of other
“sub-plants”. The sizes
involved in cement plant design are over the average
corresponding size encountered in usual projects.
A cement
production plant requires:
-
A
great variety of raw materials in large
quantities
-
Large
storage spaces
-
Great
internal and external dispatching abilities
-
Heavy
mechanical equipment
-
Special storages appropriate for the fuel (coal)
handling
-
Special industrial building structures
-
Large
energy consumption
-
High
and qualitative productivity
-
Best
available techniques (BAT) for environmental
protection
-
An
excellent system of personnel safety and
installations protection and care
-
Value
added
-
Social
contribution
-
Low
operation cost
The
plant’s installation design is fully dictated by the
operational production process in combination with
the above requirements.
As an example, during the pre-calcining process, the
meal should be previously
submitted to thermal elaboration in an environment
of 900oC temperature. This
is reached through the conveyance of the material
into a vertical cyclone
system. The meal crosses, due to gravity, the
cyclone system, to reach the
entrance of the rotary kiln. Simultaneously,
through the cyclones and having the
opposite direction, ascend the hot gases from
the kiln, producing the thermal
elaboration. For the achievement of the best,
desirable outcome of the thermal
procedure, the described cyclone system
should include at least five (5) stages
(five cyclones in vertical order). Taking
into consideration the required material
quantities and the above mentioned best
available practice, the total estimated
height of the cyclone system is between 70
and 100m. As a result, a steel or
reinforced concrete tower of appropriate height is
needed.
This tower should be equipped with additional
machinery (due to low cost
requirements) as well as big fans for hot gas flow
from the rotary kiln burner, as
described above. These special fans beside
their heavy loads, enforce
vibrations to the structure.
This makes the design of such structures absolutely
specialized, in order to
achieve the above mentioned best available practices.
The same practice is
applied to the design and study of all the
installations that constitute a cement
production plant.
A brief description of the main design
prerequisites follows below:
STORAGES
- Long spans
- Closed for
environmental reasons
- Large surfaces –
Heavy wind loads
- Optimization for
economic solution
SILOS
- Big heights –
Adequate capacity
- Special
requirement material storage
- High temperature
differences between inside and outside
- Special
foundations
- Optimization for
economic solution
MILLS
- Heavy duty
mechanical equipment
- Huge operating
machinery
- Heavy dynamic
loads
- Special
foundations
- Noise
- Optimization for
economic solution
CONVEYOR BELTS
- Special
steel structures
- Heavy
dynamic loads – Machinery in
operation
- Covering –
Environmental protection – Safety
-
Optimization for economic solution
TOWERS
- Very high
buildings (up to 100m)
- High
temperature
- Special
foundation for stability (earthquake
– wind)
-
Optimization for economic solution
3D MODELING OF
STEEL STRUCTURES
- Full
overview and easy collision and
fitting checks
-
Operational control
- Automatic
production of cutting drawings
- Exact bill
of quantities
- Easy
pre-fabrication of construction
groups and quick erection
TIME SCHEDULE
- Enables
perfect organization and facilitates
management activities
- Easy
evaluation of critical paths and
delays
-
Programming of resources (machinery,
human, cost)
- Control
and easy presentation of the program
The analysis and
design of all the above special
structures requires:
-
Specialized
knowledge and experience
-
Appropriate
software for static and dynamic
analysis, earthquake resistant
-
design,
geotechnical problems and
foundation engineering and CAD –
tools for analytical drawings
for application (rebar lists,
cutting drawings for steel
structures, e.t.c.)
-
Major parts
of the software consist of
inhouse products, specially
developed or customized for the
above requirements
The engineering Team of Cubus
Cement has been involved for
over two decades in the design
and supervision of the following
cement industry projects:
Project List |
Raw Material Crushers |
6 |
300 - 1.300 |
tn/h |
Raw Material Silos |
6 |
3.000 - 40.000 |
tn |
Pre-homo Storages |
3 |
60.000 |
tn |
Raw Mill Installation |
3 |
250 - 400 |
tn/h |
Raw Meal Silos |
6 |
8.000 - 12.000 |
tn |
Preheater Towers |
3 |
90 |
m height |
Kiln Line Bases |
3 lines |
4.500 |
tn/day |
Cooler Buildings |
3 |
4.500 |
tn/day |
Clinker Silos-Storages |
8 |
10.000 - 70.000 |
tn |
Cement Mill Buildings |
7 |
105 - 140 |
tn/h |
Cement Mill Feeding Silos |
21 |
500 |
tn |
Cement Additive Storages |
3 |
60.000 |
tn |
Cement Silos |
20 |
500 - 28.000 |
tn |
Fly Ash Silos |
3 |
8.000 |
tn |
Paking Plants/Paletizers |
30 |
80-120 |
tn/h |
Coal Yards |
3 |
200.000 |
tn |
Coal Mills |
4 |
40 |
tn/h |
Belt Conveyors, Bridges,
Towers, Pylons, Pipes, Air
Slides, Drag Chains, Bucket
Elevators, Trippers e.t.c. |
|
30.000 |
tn |
Piers and Docks for Shipping |
3 |
Length up to 400 m Width up
to 40 m Depth up to 19
m Ships up to 140.000TDW |
|
General Layout of Cement
Plants |
3 |
1.500.000 |
tn/year |
|